FF&E Decision Dates and Lead-Time Planning
Turn a quoted lead time into an actionable client decision date and document alternates for schedule-sensitive items.
Work backward from the required delivery date
Subtract the quoted weeks and time for order release, receiving, and quality checks. Confirm whether a vendor measures weeks from deposit, approval of drawings, or order acceptance.
Keep the date and the quoted duration visible
Store the required decision date with the item and record the quoted lead time in weeks. If an alternate is available, show its lead variance in the same decision document.