FF&E Substitution Budget & Lead-Time Variance Report

Document the client budget difference and quoted lead-time change before accepting a substitute.

Show the original and alternate at the same quantity

Compare extended prices for the same order quantity. A $25 difference per unit becomes a $150 room variance on six units. Keep a proposal distinct from a previously approved line.

Tie the decision back to an item code

Use the original spec code in the variance report. Include the finish or dimensions that changed and ask the client to approve, retain, or hold before procurement is updated.

Frequently asked questions

Does a zero-dollar variance need a decision?

A client may still need to approve a changed finish, size, or lead time even when the price stays the same.

Where can I review the trade variance?

Trade variances are in the Excel Substitutions tab alongside the original and alternate trade costs.

FF&E specification guides

FF&E Schedule Excel & Client Approval PDF MakerBackorder Substitution Approval Sheet for DesignersPlumbing & Lighting Fixture Schedule BuilderHospitality FF&E Procurement Schedule TemplateTrade vs Retail Markup FF&E CalculatorDesignFiles & Aalto Alternative for Small StudiosRoom-by-Room Client FF&E Approval BookVendor & Contractor FF&E Procurement ScheduleFF&E Specification Sheet TemplateResidential Living & Dining FF&E ScheduleFF&E Sourcing Spreadsheet & CSV ImportFF&E Decision Dates and Lead-Time PlanningFF&E Vendor Rollup Excel TemplateFF&E Finish and Fabric Schedule for InteriorsFF&E Client Budget Approval TemplateInterior Design FF&E Procurement HandoffFF&E Approval Revision Checklist